Answer:
"Estimating effort, time and resources needed (and available) for scheduled activities. After Define Activities, before Develop Schedule
Inputs: Activity List, Activity Attributes, Resource Calendars, Enterprise Environmental Factors
Tools: Expertise, Alternatives Analysis, Published Estimating Data, Bottom-Up Estimating, Project Management Software
Outputs: Activity Resource Requirements, Resource Breakdown Structure, Project Documet Updates"