Start -> A -> B -> C -> D -> E -> Finish. You have the following process information: Process A requires 10 minutes per widget. Process B does 4 widgets per hour. Process C does 4.6 widgets per hour. Process D can do 28 widgets per 8-hour shift. Process E takes 16 minutes per widget. What is the process time of the system? minutes per widget. (Please round to the nearest integer; if you would like to enter 12.345, please type in a 12.) Which process is the bottleneck? If you tied yourself to a widget just as it started Process A, how many minutes later would you find yourself done with Process E? minutes. (Please round to the nearest integer; if you would like to enter 12.345, please type in a 12. Hint: this is another way of asking for the throughput time.) Would it help make more widgets per day if we could speed up Process A by one minute per widget? . (Please enter yes or no). Say we didn't end up changing Process A after all. If we could speed Process D up by 5 minutes per widget, what would the new process time of the system be? minutes. (Please round to the nearest integer; if you would like to enter 12.345, please type in a 12.) Say we did speed up Process D by those 5 minutes per widget. Where is the bottleneck of the system now?

Respuesta :

The process time of the system is 19 minutes per widget.

A widget is a comparatively straightforward and easy-to-use computer code application or element created for one or additional totally different computer code platforms. A table accent or applications programme is an example of a widget, complete computer programme, in distinction with a additional complicated application like a computer programme or applications programme.

A bottleneck is a method in an exceedingly chain of processes, such its restricted capability reduces the capability of the complete chain. The results of having a bottleneck ar stalls in production, provide buy in, pressure from customers, and low worker morale.

To learn more about bottleneck here

brainly.com/question/13302820

#SPJ4