The project management concept that can best be applied to situations such as r&d, computer systems design, and military invasions is:________

Respuesta :

The project management concept that can be applied here is- Program Evaluation Review Technique (PERT) .

The Program Evaluation Review Technique (PERT) is a project management planning tool used to estimate how long it will take to complete a project realistically. PERT charts are used to plan tasks within a project, which makes scheduling and coordinating team members easier.

PERT and critical path are both used to visualize the timeline and work that must be completed for a project. PERT, on the other hand, allows you to create three different time estimates for the project: The shortest amount of time each task will take, the most likely amount of time, the longest amount of time tasks may take if things do not go as planned, PERT is calculated backward from a fixed end date because contractor deadlines are typically not movable.

Learn more about The Program Evaluation Review Technique (PERT) here: