The discounted payback period for the project is 2.33 years.
Time Cashflow PVF at 8% Present value Cumulative Present value
0 -$100 1 -100 -100
1 40 0.925926 37.03704 -62.963
2 50 0.857339 42.86694 -20.096
3 60 0.793832 47.62993 27.53391
Note
Discounted payback period = 2 Years + 20.096/47.6299
Discounted payback period = 2 Years + 0.33
Discounted payback period = 2.33 years.
Therefore, the discounted payback period for the project is 2.33 years.
Missing word includes "Compute the discounted payback period for a project with the following cash flows received uniformly within each year and with a required return of 8%: Initial Outlay = $100 Cash Flows: Year 1 = $40 Year 2 = $50 Year 3 = $60"