Answer:
IRR= -4.57%
NPV= -5,903.21
Explanation:
Giving the following information:
Cf0= -20,000
Cf1= 6,000
Cf2= 5,000
Cf3= 4,000
Cf4= 3,000
Rate of retun= 12%
To calculate the project IRR and NPV, we need to use the financial calculator:
Function= Cash
I%= 12
1= -20,000
2= 6,000
3= 5,000
4= 4,000
5= 3,000
IRR= SOLVE = -4.57%
Now, back to I%= 12;
NPV= SOLVE = -5,903.21