Simkin Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below:
Hours Wait time 22.0 Process time 6.1 Inspection time 1.5 Move time 4.1 Queue time 6.2
The manufacturing cycle efficiency (MCE) was closest to:______. (Round your intermediate calculations to 1 decimal place.)

Respuesta :

Answer:

0.34

Explanation:

Calculation to determine what The manufacturing cycle efficiency (MCE) was closest to:

First step is to calculate the Throughput time using this formula

Throughput time = Process time + inspection time + move time + queue time

Let plug in the formula

Throughput time=6.1+1.5+4.1+6.2

Throughput time=17.9

Now let calculate the MEC using this formula

MEC = process time / throughput time

Let plug in the formula

MEC=6.1/17.9

MEC =0.34

Therefore The manufacturing cycle efficiency (MCE) was closest to:0.34