It takes a groundskeeper 35 minutes to prepare a Little League baseball field for a game. It takes his assistant 45 minutes to prepare the same field. How long will it take if they work together to prepare the field?

Respuesta :

a) It takes a groundskeeper 45 minutes to prepare a softball field for a game. It takes his assistant 50 minutes to prepare the same field. How long will it take if they work together to prepare the field?

G does 1/45 job per minute

A does 1/50 job per minute

Together, they do 1/45 + 1/50 = 19/450 jobs/minute

--> 450/19 minutes to do the job

You can use a shortcut, product/sum

50*45/(50+45) = 2250/95

= 450/19

--------------------------------

b) It takes the owner/operator of a dog kennel 7 hours to clean all of the cages. It takes his assistant 4 hour(s) more than that to clean the same cages. How long will it take if they work together?

This is 7 and 11 hours.

7*11/(7+11) = 77/18 hours

= ~ 4.28 hours