Answer:
a-1. NPV for the project is $8,381,576.17
a-2. A. Yes. Accept the Project.
b. 40.84 % and 40.84 %
Explanation:
The Net Present Value can be determined using a Financial Calculator as follows :
-38,600,000 CFj
62,600,000 CFj
- 11,600,000 CFj
11 % I/YR
Shift NPV $8,381,576.17
A Company should accept projects that have a positive Net Present Value.Therefore, Accept this project.
Calculation of the Internal Rate of Return using a Financial Calculator :
-38,600,000 CFj
62,600,000 CFj
- 11,600,000 CFj
Shift IRR 40.84 %