Answer:
Explanation:
Given
Setup cost =$50
Material cost = $20
= $20×$20
= $400
Purchased cost = $88.50
Learning rate (P) = 90%
Labor cost is $8.50, and it requires 5 hours to produce the first unit. Total time required for the production of 20 units is
= 5×14.608
= $73.04
The value 14.608 is the total time factor which has been taken from table 7S.1 and the time required for the production of 20 units at the rate of 90% is 14.608. Hence, the labor cost for the production of 20 units will be calculated using the following method.
Cost of labor for production of 20 units
= 8.50×73.04
= $620.84
Hence,
In the problem, it has been given that the overhead cost is 50% of the labor material, and setup cost. Hence,
= 50/100 (620.84+50+400)
= 0.5×(1070.84)
= $535.42
Hence total cost
$535.42 +$1070.84
=$ 1606.26
Hence, the cost of production of 20 units is calculated by the following method.
= $1606.26÷20
=$80.313
Therefore, the unit cost is $80.313/unit.
Ans B:
The minimum production quantity important to make the production cost less than the purchase cost is calculated by the trial-and-error method. Now, let's take average unit cost when the 10 units are produced.
Setup cost =$50
Material cost = $20
= $20×$10
= $200
Labor cost is $8.50, and it requires 5 hours to produce the first unit. Total time required for the production of 10 units is
=5×7.994
= $39.97
The value 7.994 is the total time factor which has been taken from table 7S.1 and the time required for the production of 10 units at the rate of 90% is 7.994. Therefore, the labor cost for the production of 10 units will be calculated by the following method.
The cost of production of 20units
8.50×7.994×5
= $339.745