Answer:
4.47
Explanation:
The computation of the standard deviation of lead time is shown below:
= √lead time × standard deviation of demand
= √ 5 days × 4
= √20
= 4.47
We simply applied the above formula to determine the standard deviation of demand during lead time
Hence, all the other items would be ignored