Rebel Sound Inc. produced 30,000 audio devices last month. Rebel started the month with $10,000 worth of inventory in Finished Goods. The company incurred $15,000 of various utility and rent charges on their factory, paid $50,000 for raw materials to use in production, and paid employees $60,000 in wages. During the month, inventory costing $120,000 was completed and transferred to the Finished Goods Inventory. At the end of the month, Rebel had $5,000 of Inventory in Finished Goods, $6,000 in Materials Inventory, and $24,000 still in Work in Process.

Required:
What was Rebel Sound Inc Cost of Goods Manufactured for the month?

Respuesta :

Zviko

Answer:

$120,000

Explanation:

Step 1 Prepare a Cost of Manufacturing Schedule

Materials ($50000-$6,000)                              $44,000

Various utility and rent charges on factory       $15,000

Salaries and Wages                                           $60,000

Other Costs(Balancing figure)                           $35,000

Less Work in Process                                       ($24,000)

Cost of Goods Manufactured                           $120,000

Step 2 Prepare a cost of Goods Sold Schedule

Opening  inventory in Finished Goods             $10,000

Add Cost of Goods Manufactured                  $120,000

Less Closing  inventory in Finished Goods      ($5,000)

Cost of Goods Sold                                          $125,000