Answer:
13.3%
Explanation:
OEE= Availability × Performance × Quality
Availability = Run Time/ Planned Production Time
Run time = 3*100 = 300 + 0.2* 300 = 1.2 *300 = 360 mins
Planned Production time = 24*60 = 1440 mins
Availability = 360/1440 = 1/4 = 25%..............1
Performance = (Ideal Cycle Time × Total Count) / Run Time
Ideal Cycle Time = 2 min (Only the processing time)
Total Count= 100+20 = 120
Performance = 2*120/360 =66.67% .............2
Quality = 100%-20% = 80%.......3
Frpm 1,2,3
OEE=25% * 66.67 % * 80% =
0.13334=13.3%