Kerekes Manufacturing Corporation has prepared the following overhead budget for next month.
Activity level 2,700 machine-hours
Variable overhead costs:
Supplies $ 12,690
Indirect labor 23,220
Fixed overhead costs:
Supervision 16,500
Utilities 6,100
Depreciation 7,100
Total overhead cost $ 65,610
The company's variable overhead costs are driven by machine-hours.
What would be the total budgeted overhead cost for next month if the activity level is 2,600 machine-hours rather than 2,700 machine-hours?
Multiple Choice
$63,670
$63,180
$64,280
$65,610