Answer:
a.$15.07 per unit
Explanation:
Using a single plantwide overhead rate based on direct labor hours each product is assigned $15.07 of overhead per unit.
Plantwide overhead rate = Total Budgeted Overhead/ Total Budgeted Direct Labor Hours
Plantwide overhead rate = $320,900/ 21,300= $ 15.065= $ 15.07
Overhead Total Direct Labor Hours DLH per Product A B
Painting Dept. $255,200 10,100 3 11
Finishing Dept. 65,700 11,200 6 7
Totals $320,900 21,300 9 1