Answer:
underapplied for 2.037.000
Explanation:
[tex]\frac{Cost\: Of \:Manufacturing \:Overhead}{Cost \:Driver}= Overhead \:Rate[/tex]
we divide the expected overhead by the expected machine hours:
11,270,000 / 161,000 = $70
applied overhead = actual machine hours x rate
85,000 MH x $70 = 5,950,000
actual overhead 7,987,000
As we applied less than actual cost we underapplied the overhead.
7,987,000 - 5,950,000 = 2.037.000