The critical path of a network is the A. shortest time path through the network. B. path with the most activities. C. longest time path through the network. D. path with the fewest activities.

Respuesta :

Answer: Option [C] : The longest time path through the network.

Explanation:

The critical path of a network is the longest time path through the network.