ou have been hired as a contract project manager for Grapevine Vineyards. Grapevine wants you to design an Internet wine club for its customers. One of the activities for this project is the installation and testing of several new servers. You know from past experience it takes about 16 hours per server to accomplish this task. Since you're installing 10 new servers, you estimate this activity to take 160 hours. Which of the estimating techniques have you used?

Respuesta :

Answer:

Time and cost estimation/ management.

Explanation:

A time/cost estimate is the approximation of the time/cost of a program, project, or operation. The time/cost estimate is the product of the time/cost estimating process. The time/cost estimate has a single total value and may have identifiable component values.

As calculated by the project manager for grapevine vineyards.