Answer:
45
Explanation:
The formula to compute the number of parts is shown below:
= Demand × lead time × (1 + safety factor) ÷ kanban cards
= 300 units × 45 minutes × (1 + 20%) ÷ 6
= 300 × 0.75 hours × 1.2 ÷ 6
= 45
The 45 minutes would be 0.75 hours i.e 45 minutes ÷ 60 minutes = 0.75 hours.
So we consider all the components which are given in the question. Hence, all the information is relevant