The table shows five activities (in days) for a project. Use PERT (Program Evaluation and Review Technique) to calculate the expected time of completion for activity B.


A. 11 days


B. 6.5 days


C. 9 days


D. 8 days

The table shows five activities in days for a project Use PERT Program Evaluation and Review Technique to calculate the expected time of completion for activit class=

Respuesta :

Answer:

B. 6.5 days

Step-by-step explanation:

The estimated time for completing an activity can be computed if we have optimistic time, most likely time and pessimistic time

The formula is:

[tex]T_e = \frac{T_0+4T_m+T_p}{6} \\where\\T_0 = Optimistic\ Time\\T_m = Most\ likely\ time\\T_p=Pessimistic\ time[/tex]

For activity B:

[tex]T_0=3\\T_m=6\\T_p=12[/tex]

Putting the values in the formula

[tex]T_e = \frac{3+4(6)+12}{6}\\T_e=\frac{3+24+12}{6}\\T_e=\frac{39}{6}\\T_e=6.5\ days[/tex]

The correct answer is:

B. 6.5 days ..

Answer:

the answer is 8

Step-by-step explanation:

i took the test