After an art's first PI planning, what action can the Release Train Engineer (RTE) take to help optimize the ART backlog readiness for the next PI?
A. Conduct a retrospective to analyze the PI planning process.
B. Implement changes to the team's daily schedule.
C. Ignore backlog readiness and focus on current sprint tasks.
D. Request additional resources without assessing the current situation.