Which option identifies the section of the project charter represented in the following scenario?
For the past five years, students at New School have been in desperate need of a playground. The closest playground is a mile away, at Safe
Park. Our project is to design a playground for the students and to find funding in the community to support it.
O executive summary
O constraints
O project objectives
O project development cycle

Respuesta :

Answer:

Executive Summary

Explanation:

It is Executive Summary because I used process of elimination. Constraints are set backs. Project objectives are the goals that you want to achieve. Project development cycle are basically the steps that will be used.